Project: I-70 and 110th Street Interchange
Summary
The I-70 and 110th Street Interchange was rebuilt and I-70 was widened between 465 and 1/4 miles west of 110th Street, toll booths were moved, and US 24 was realigned (State Street).
Characteristics and Setting
Classification/Type
Interchange
Transportation Mode
Highway
Usage
3,270
Length (mi)
Economic Distress
0.72
Population Density (ppl/sq mi)
1,015
Population Growth Rate (%)
-0.6%
Employment Growth Rate (%)
0.8%
Market Size
823,293
Airport Travel Distance (mi)
24.0667
Topography
13
Geography
Region
Great Lakes / Plains
State
KS
County
Wyandotte
City
Kansas City
Urban/Class Level
Mixed
Local Area
N/A
Impact Area
N/A
Transportation System
None
Timing
Initial Study Date
N/A
Post Construction Study Date
2008
Construction Start Date
1995
Construction End Date
2001
Months Duration
N/A
Costs
Project Year of Expenditure (YOE)
N/A
Planned Cost (YOE $)
N/A
Actual Cost (YOE $)
$49,700,000
Actual Cost (2022$)
$101,931,200
Pre/Post Conditions
NOTE: All pre/post dollar values are in 2022$
Transportation
| Measure | Pre project | Post project | Change | % Change |
|---|
Impacts
NOTE: All impact dollar values are in 2022$
| Measure | Total |
|---|
Case Location
Narrative
I-70 AND 110TH STREET INTERCHANGE
Attachments
Transp Infrastructure Investments and Econ Growth - Five KS Case Studies