Project: Bennington Bypass, VT 279

Summary

The Bennington Bypass, also known as VT 279, provides an alternative route around the center of Bennington, Vermont which saves time primarily for winter ski tourists.

Characteristics and Setting

Classification/Type Bypass (around Community)
Transportation Mode Highway
Usage 3,700
Length (mi) 4.20
Economic Distress 0.80
Population Density (ppl/sq mi) 54
Population Growth Rate (%) -0.2%
Employment Growth Rate (%) 1.0%
Market Size 18,050
Airport Travel Distance (mi) 85.0000
Topography 16

Geography

Region New England/Mid-Atlantic
State VT
County Bennington
City Bennington
Urban/Class Level Metro
Local Area N/A
Impact Area N/A
Transportation System None

Timing

Initial Study Date 1998
Post Construction Study Date 2008
Construction Start Date 1999
Construction End Date 2004
Months Duration N/A

Costs

Project Year of Expenditure (YOE) 2000
Planned Cost (YOE $) N/A
Actual Cost (YOE $) $26,000,000
Actual Cost (2022$) $51,725,600

Pre/Post Conditions

NOTE: All pre/post dollar values are in 2022$

Transportation

Measure Pre project Post project Change % Change

Impacts

NOTE: All impact dollar values are in 2022$

Measure Total

Case Location

View Map

Narrative

Bennington Bypass, VT 279

Attachments

No attachments were submitted.