Project: MARTA Lindberg Station

Summary

The Lindbergh Station City Center project was planned as a mixed-use transit-oriented development. Twenty four million dollars were invested by MARTA which included platform additions, stairs, escalators, elevators, concourse areas, fare gates, an upgraded bus transfer system, and a ground-level street plaza. The development around the station included 1 million square feet of office space, 300,000 square feet of retail space, and 714 residential units.

Characteristics and Setting

Classification/Type In-fill Transit Station
Transportation Mode Heavy Rail
Usage 9,689
Length (mi) 0.00
Economic Distress 1.00
Population Density (ppl/sq mi) 1,825
Population Growth Rate (%) 2.6%
Employment Growth Rate (%) 1.1%
Market Size 1,442,317
Airport Travel Distance (mi) 20.0000
Topography 5

Geography

Region Southeast
State GA
County Fulton
City Lindberg/Morosgo
Urban/Class Level Metro
Local Area N/A
Impact Area N/A
Transportation System Transit

Timing

Initial Study Date 2000
Post Construction Study Date 2008
Construction Start Date 2000
Construction End Date 2004
Months Duration N/A

Costs

Project Year of Expenditure (YOE) 2001
Planned Cost (YOE $) N/A
Actual Cost (YOE $) $26,000,000
Actual Cost (2022$) $53,324,200

Intermodal Characteristics:

Intermodal Actual Cost (YOE)
$24,000,000
Intermodal Actual Cost (2022$)
$31,569,554
Highway Road Access Improvement Cost (YOE $)
$2,000,000

In-fill Transit Station

Average Annual Daily Traffic
43,000
Number of Parking Spaces
10,461

Pre/Post Conditions

NOTE: All pre/post dollar values are in 2022$

Transportation

Measure Pre project Post project Change % Change

Impacts

NOTE: All impact dollar values are in 2022$

Measure Total

Case Location

View Map

Narrative

MARTA Lindberg Station

Attachments

No attachments were submitted.