Project: Anderson Regional Transportation Center, Woburn, MA

Summary

The Anderson Regional Transportation Center (ARTC) is a multi-modal transit hub with commuter rail and bus service to Boston and points north. The project involved cleanup of a superfund site, and construction of the intermodal facility, new surface roads and a highway interchange.

Characteristics and Setting

Classification/Type In-fill Transit Station
Transportation Mode Commuter Rail
Usage 720
Length (mi) 0.00
Economic Distress 0.87
Population Density (ppl/sq mi) 1,781
Population Growth Rate (%) 220.0%
Employment Growth Rate (%) 220.0%
Market Size 1,742,936
Airport Travel Distance (mi) 12.0000
Topography 9

Geography

Region New England/Mid-Atlantic
State MA
County Middlesex
City Woburn
Urban/Class Level Metro
Local Area N/A
Impact Area N/A
Transportation System Highway and Rail

Timing

Initial Study Date 1996
Post Construction Study Date 2007
Construction Start Date 1997
Construction End Date 2001
Months Duration N/A

Costs

Project Year of Expenditure (YOE) 2000
Planned Cost (YOE $) N/A
Actual Cost (YOE $) $57,000,000
Actual Cost (2022$) $122,343,100

Intermodal Characteristics:

Intermodal Actual Cost (YOE)
$37,000,000
Intermodal Actual Cost (2022$)
$51,737,149
Highway Road Access Improvement Cost (YOE $)
$20,000,000

In-fill Transit Station

Average Annual Daily Traffic
6,500
Number of Parking Spaces
N/A

Pre/Post Conditions

NOTE: All pre/post dollar values are in 2022$

Transportation

Measure Pre project Post project Change % Change

Impacts

NOTE: All impact dollar values are in 2022$

Measure Total

Case Location

View Map

Narrative

Anderson Regional Transportation Center, Woburn, MA

Attachments

No attachments were submitted.