Project: Fairburn CSX Industry Yard, Fairburn,GA
Summary
The Fairburn CSX Intermodal Center was built to create a high volume rail corridor for reliable intermodal service on the lines connecting Southern California ports with Atlanta and with the rest of the southeast region.
Characteristics and Setting
Classification/Type
Freight Terminal
Transportation Mode
Highway
Usage
10,060
Length (mi)
Economic Distress
1.04
Population Density (ppl/sq mi)
1,825
Population Growth Rate (%)
2.6%
Employment Growth Rate (%)
1.1%
Market Size
1,442,317
Airport Travel Distance (mi)
20.0000
Topography
5
Geography
Region
Southeast
State
GA
County
Fulton
City
Fairburn
Urban/Class Level
Rural
Local Area
N/A
Impact Area
N/A
Transportation System
None
Timing
Initial Study Date
N/A
Post Construction Study Date
2007
Construction Start Date
1997
Construction End Date
1999
Months Duration
N/A
Costs
Project Year of Expenditure (YOE)
1998
Planned Cost (YOE $)
N/A
Actual Cost (YOE $)
$156,000,000
Actual Cost (2022$)
$342,752,000
Intermodal Characteristics:
- Intermodal Actual Cost (YOE)
- $150,000,000
- Intermodal Actual Cost (2022$)
- $198,131,595
- Highway Road Access Improvement Cost (YOE $)
- $6,000,000
Freight Terminal
- Container Volume (Metric Tons)
- N/A
- Container Volume (TEUs)
- 420,000
- All Cargo Volume (Metric Tons)
- N/A
Pre/Post Conditions
NOTE: All pre/post dollar values are in 2022$
Transportation
| Measure | Pre project | Post project | Change | % Change |
|---|
Impacts
NOTE: All impact dollar values are in 2022$
| Measure | Total |
|---|
Case Location
Narrative
FAIRBURN INTERMODAL CENTER FULTON COUNTY, GEORGIA
Attachments
No attachments were submitted.