Project: Ted Williams Freeway

Summary

The Ted Williams Highway (State Route 56 (SR 56)) runs from Interstate 5 in the Carmel Valley neighborhood of San Diego to Interstate 15.

Characteristics and Setting

Classification/Type Connector Highway
Transportation Mode Highway
Usage 110,146
Length (mi) 9.70
Economic Distress 1.67
Population Density (ppl/sq mi) 702
Population Growth Rate (%) 0.5%
Employment Growth Rate (%) 1.3%
Market Size 1,094,379
Airport Travel Distance (mi) 20.4500
Topography 21

Geography

Region Rocky Mountain / Far West
State CA
County San Diego
City San Diego
Urban/Class Level Metro
Local Area N/A
Impact Area N/A
Transportation System Highway

Timing

Initial Study Date 1992
Post Construction Study Date 2006
Construction Start Date 1992
Construction End Date 2004
Months Duration N/A

Costs

Project Year of Expenditure (YOE) 2004
Planned Cost (YOE $) N/A
Actual Cost (YOE $) $220,000,000
Actual Cost (2022$) $402,184,100

Pre/Post Conditions

NOTE: All pre/post dollar values are in 2022$

Transportation

Measure Pre project Post project Change % Change

Impacts

NOTE: All impact dollar values are in 2022$

Measure Total

Case Location

View Map

Narrative

Ted Williams Freeway