Project: Branson W (Ozark Mt. Highroad)
Summary
The Ozark Mountain Highroad (SR 465) was constructed in the mid-'90's in reaction to a tourism boom that occurred in Branson, but failed to relieve the congestion of SR 76.
Characteristics and Setting
Classification/Type
Connector Highway
Transportation Mode
Highway
Usage
2,970
Length (mi)
7.50
Economic Distress
1.22
Population Density (ppl/sq mi)
69
Population Growth Rate (%)
1.8%
Employment Growth Rate (%)
2.8%
Market Size
29,509
Airport Travel Distance (mi)
56.3378
Topography
19
Geography
Region
Great Lakes / Plains
State
MO
County
Stone & Teney Counties
City
Branson
Urban/Class Level
Rural
Local Area
N/A
Impact Area
N/A
Transportation System
Highway
Timing
Initial Study Date
1969
Post Construction Study Date
1999
Construction Start Date
1993
Construction End Date
1998
Months Duration
N/A
Costs
Project Year of Expenditure (YOE)
1998
Planned Cost (YOE $)
N/A
Actual Cost (YOE $)
$78,700,000
Actual Cost (2022$)
$182,079,500
Pre/Post Conditions
NOTE: All pre/post dollar values are in 2022$
Transportation
| Measure | Pre project | Post project | Change | % Change |
|---|
Impacts
NOTE: All impact dollar values are in 2022$
| Measure | Total |
|---|
Case Location
Narrative
Branson W (Ozark Mt. Highroad)