Project: E-470 Denver

Summary

E-470 is a private, 47-mile long toll road that forms an outer beltway around the eastern side of Denver from Colorado C-470/Interstate 25 in the south to Interstate 25/Northwest Parkway in the north.

Characteristics and Setting

Classification/Type Beltway (within Metro Area)
Transportation Mode Highway
Usage 160,818
Length (mi) 47.00
Economic Distress 1.24
Population Density (ppl/sq mi) 425
Population Growth Rate (%) 1.2%
Employment Growth Rate (%) 0.5%
Market Size 937,204
Airport Travel Distance (mi) 38.6934
Topography 9

Geography

Region Rocky Mountain / Far West
State CO
County Boulder, Adams, Denver, Douglas, Arapahoe
City Denver
Urban/Class Level Metro
Local Area N/A
Impact Area N/A
Transportation System Highway

Timing

Initial Study Date 1987
Post Construction Study Date 2006
Construction Start Date 1988
Construction End Date 2003
Months Duration N/A

Costs

Project Year of Expenditure (YOE) 1999
Planned Cost (YOE $) N/A
Actual Cost (YOE $) $1,547,215,594
Actual Cost (2022$) $3,320,896,600

Pre/Post Conditions

NOTE: All pre/post dollar values are in 2022$

Transportation

Measure Pre project Post project Change % Change

Impacts

NOTE: All impact dollar values are in 2022$

Measure Total

Case Location

View Map

Narrative

E-470 Denver