Project: Oresund Bridge
Summary
The Oresund Bridge, linking the cities of Copenhagen, Denmark and Malmo, Sweden. is a 16 kilometer (10 mile) combined rail and road bridge-tunnel spanning the Oresund strait.
Characteristics and Setting
Classification/Type
Bridge
Transportation Mode
Highway
Usage
18,500
Length (mi)
4.87
Economic Distress
0.00
Population Density (ppl/sq mi)
66
Population Growth Rate (%)
0.0%
Employment Growth Rate (%)
0.0%
Market Size
0
Airport Travel Distance (mi)
0.0000
Topography
1
Geography
Region
International
State
Denmark, Sweden
County
N/A
City
None
Urban/Class Level
Metro
Local Area
N/A
Impact Area
N/A
Transportation System
Highway
Timing
Initial Study Date
1994
Post Construction Study Date
2004
Construction Start Date
1994
Construction End Date
2000
Months Duration
N/A
Costs
Project Year of Expenditure (YOE)
2000
Planned Cost (YOE $)
N/A
Actual Cost (YOE $)
$2,147,483,647
Actual Cost (2022$)
$4,490,004,800
Pre/Post Conditions
NOTE: All pre/post dollar values are in 2022$
Transportation
| Measure | Pre project | Post project | Change | % Change |
|---|
Impacts
NOTE: All impact dollar values are in 2022$
| Measure | Total |
|---|