Project: Danville, Virginia, I-785 Beltway

Summary

The beltway creates a semi-circle road around Danville, taking truck traffic off of US 29 through downtown. The new road, constructed between 1987 and 2004, was built to Interstate standards. It is part of a joint effort between Virginia and North Carolina

Characteristics and Setting

Classification/Type Beltway (within Metro Area)
Transportation Mode Highway
Usage 20,100
Length (mi) 25.00
Economic Distress 0.57
Population Density (ppl/sq mi) 2,468
Population Growth Rate (%) -0.6%
Employment Growth Rate (%) -0.6%
Market Size 46,274
Airport Travel Distance (mi) 66.5000
Topography 10

Geography

Region Southeast
State VA
County Danville
City Danville
Urban/Class Level Metro
Local Area N/A
Impact Area N/A
Transportation System Highway

Timing

Initial Study Date 1987
Post Construction Study Date 2006
Construction Start Date 1987
Construction End Date 2004
Months Duration N/A

Costs

Project Year of Expenditure (YOE) 2004
Planned Cost (YOE $) N/A
Actual Cost (YOE $) $203,000,000
Actual Cost (2022$) $469,658,700

Pre/Post Conditions

NOTE: All pre/post dollar values are in 2022$

Transportation

Measure Pre project Post project Change % Change

Impacts

NOTE: All impact dollar values are in 2022$

Measure Total

Case Location

View Map

Narrative

Danville, Virginia, I-785 Beltway

Attachments

Economic Impact of Freeway Bypass Routes in Medium Size Cities