Project: Highway 141: Page-Olive Connector

Summary

The 2-mile long Page-Olive Connector, extends the Maryland Heights Expressway from MO 364 (Page Avenue) to MO 340 (Olive Boulevard) under a design-build contract from the St. Louis County Department of Highways & Traffic and Public Works in St. Louis County, Missouri.

Characteristics and Setting

Classification/Type Connector Highway
Transportation Mode Highway
Usage 28,243
Length (mi) 2.00
Economic Distress 1.30
Population Density (ppl/sq mi) 1,954
Population Growth Rate (%) -0.1%
Employment Growth Rate (%) -0.3%
Market Size 1,881,781
Airport Travel Distance (mi) 11.6000
Topography 14

Geography

Region Great Lakes / Plains
State MO
County St. Louis
City Chesterfield & Maryland Heights
Urban/Class Level Metro
Local Area N/A
Impact Area N/A
Transportation System None

Timing

Initial Study Date 2009
Post Construction Study Date 2017
Construction Start Date 2010
Construction End Date 2012
Months Duration 29

Costs

Project Year of Expenditure (YOE) 2010
Planned Cost (YOE $) N/A
Actual Cost (YOE $) $52,500,000
Actual Cost (2022$) $73,363,500

Pre/Post Conditions

NOTE: All pre/post dollar values are in 2022$

Transportation

Measure Pre project Post project Change % Change

Impacts

NOTE: All impact dollar values are in 2022$

Measure Total

Case Location

View Map

Narrative

Highway 141: Page-Olive Connector