Project: Cattaraugus Economic Development Zone Infrastructure

Summary

Construction of a two lane road from the Town of Allegany, eastward to the City of Olean, including water mains and sanitary sewers. The road also supported an industrial park.

Characteristics and Setting

Classification/Type Access Road
Transportation Mode Highway
Usage 1,014
Length (mi) 2.00
Economic Distress 0.76
Population Density (ppl/sq mi) 62
Population Growth Rate (%) -0.6%
Employment Growth Rate (%) 0.4%
Market Size 10,078
Airport Travel Distance (mi) 52.6333
Topography 15

Geography

Region New England/Mid-Atlantic
State NY
County Cattaraugus
City Allegany
Urban/Class Level Rural
Local Area N/A
Impact Area N/A
Transportation System None

Timing

Initial Study Date N/A
Post Construction Study Date 2000
Construction Start Date 1989
Construction End Date 1992
Months Duration N/A

Costs

Project Year of Expenditure (YOE) N/A
Planned Cost (YOE $) N/A
Actual Cost (YOE $) $622,400
Actual Cost (2022$) $1,674,400

Pre/Post Conditions

NOTE: All pre/post dollar values are in 2022$

Transportation

Measure Pre project Post project Change % Change

Impacts

NOTE: All impact dollar values are in 2022$

Measure Total

Case Location

View Map

Narrative

CATTARAUGUS ACCESS ROAD

Attachments

ARC Public Works 2000